Sheet Pile Construction in Cideng River Being Accelerated

We target to finish it within four months ahead

The South Jakarta Water Resources (SDA) Sub-agency is accelerating the Cideng River's sheet pile construction on Jalan Rasamala VII, RT 11/13, Menteng Dalam, Tebet.

Maintenance Division Head, Junjung said that the sheet pile construction is carried out up to 125 meters long with 200 centimeters high, and 50 centimeters deep.

Sheet Pile on Jalan Cipete II Being Repaired

"It is done because the old one was broken," he expressed, Wednesday (11/2).

He stated it has been ongoing since September 28, 2022, through 15 workers.

"We target to finish it within four months ahead," he stated.

Linked News
Popular News indeks
  1. Joint Personnel Handle Inundation at Matraman Underpass

    access_time08-02-2025 remove_red_eye362 personBudhi Firmansyah Surapati
  2. North Jakarta Becomes a Pilot Project for Urban Waste Management in Indonesia

    access_time10-02-2025 remove_red_eye326 personAldi Geri Lumban Tobing
  3. Commission E Legislator Invites Resident to Attend Free Cancer Screening

    access_time07-02-2025 remove_red_eye297 personDessy Suciati
  4. 22 Cubic Meters Fire Waste in Kebong Kosong Transported

    access_time07-02-2025 remove_red_eye292 personBudhi Firmansyah Surapati
  5. Preventing FMD, 181 Cattle in East Jakarta Vaccinated

    access_time07-02-2025 remove_red_eye278 personNurito